During the design process, the cobble berm was seen as a means of providing assurance that future erosion would not damage the relocated bike path nor result in future impacts to the Fairgrounds. The final design was based upon the concept sketch below. The 'retreat zone' is the area of the parking lot, approximately 20 meters (64.5 ft) wide. (The current work (Phase 1) removes about half of the 1800 feet of parking lot.)


The following photos show the sequence of events (so far), looking toward the rivermouth from the east end of the project area:







The cobble is being transported by truck from the Corps of Engineers project on Santa Paula Creek. ($4 million to clean out lower Santa Paula Creek to increase safe capacity prior to major storms) The Surfers' Point project calls for 30,000 cubic yards (about 3,000 truck loads) of cobble, and approximately 15,000 cubic yard of sand.


Once approximately 3 feet of cobble has been delivered and graded flat, sand is then placed on top and flushed with water hoses so it fills the spaces between the cobble. Additional layers of cobble and sand will gradually build up the berm to meet engineering specifications.

The scale of the berm is evident in this photo of the retreat zone - here the first 3 foot layer of cobble has been placed, and sand is being worked into the spaces.

This drawing shows an engineering 'plan view' of the buried cobble berm, illustrating its alignment along the backshore in relation to the new parking lot and bike path:

More: http://www.venturariver.org/search/label/Surfers%27%20Point