Matilija Dam Ecosystem Restoration Campaign Update 2013-2014

Matilija Coalition:   One of the most common questions we are asked, whether at public events or just hanging out at the beach, is "when is that dam coming out?"   Although recent progress on actual dam removal has been painfully slow, there remains considerable interest and support within our community.

The Matilija Coalition continues to provide public outreach and education on Matilija Dam. We conducted 4 field tours in 2013, most notably the SERCAL conference (Society for Ecological Restoration California Chapter SERCAL conference 2013).   This month I was invited to give a short update to the Ojai Rotary Club.  We also work with classes from UCSB, Ojai Valley School, and Ventura College.  In 2014 we will also host a fieldtrip for Ventura High School AP science class and another AP Science group called "Get Inspired".

Dam Removal Update:
Unfortunately, little progress has been made since the 2004 federal feasibility plan was approved by Congress in 2007.  The original schedule had dam removal slated for 2012, but that date slipped by quickly with a lack of federal funding and fundamental problems with the plan.  As detailed design
progressed it was evident that actual costs for the $145M project were quickly surpassing $200M! We have been working with federal, state, and local agencies to resolve these issues since 2008.  Milestones in this effort are documented at VenturaRiver.org 

In 2012, the Matilija Dam "Technical Advisory Committee (TAC)" completed a work plan for the next steps in resolving the issues with removing Matilija Dam.  The studies will include:

Task 1: Dam Removal Plans and Costs - to complete a screening and evaluation process of feasible dam removal and interim notch concepts, and ultimately to complete a conceptual design of up to two (2) preferred concepts that could move forward into permitting and implementation.

Task 2: Sediment Analysis of interim and dam removal schemes - evaluate the in-channel and reservoir-area responses to the proposed full dam removal initial options and concepts that will be screened and evaluated in Task 1, with a primary reliance on the simulation of sediment transport processes to evaluate downstream sedimentation and associated flooding risk, as well as (included in Task 1) geomorphologic changes, short- and long-term habitat impacts, and water quality.

Task 3: Robles Diversion Mitigation - develop methods to mitigate the impact to water supply through supplying water of acceptable quality during the period of turbidity impact. The work of Task 3 would be done in close collaboration with Tasks 1 and 2.

The completed TAC reports may be downloaded at matilijadam.org

In 2013 a consultant team was selected to perform the additional studies recommended by the TAC.  A contract was recently approved by the Ventura County Board of Supervisors, with the work to be sponsored by the California Coastal Conservancy.  Work should begin in March 2014.  A meeting will be scheduled around the May time frame with the project "Design Oversight Group" in order to consolidate information and brainstorm dam removal alternatives.  The studies are anticipated to take about 18 months, at which point we should have a short list of potential project alternatives which will require still more engineering for implementation.

The Matilija Coalition will continue to advocate for the most cost-effective plan possible.  Recognizing that we are in an era of greatly reduced federal funding necessitates simplifying the project in order to reduce costs significantly.  For an example of the negative impacts of federal spending cuts, visit the beaches of Port Hueneme. Read more here: beach-erosion-and-federal-funding


Upcoming Events:

Salmonid Restoration Federation (SRF) Conference 2014
This year's conference returns to Santa Barbara, CA.   SRF promotes restoration, stewardship, and recovery of California native salmon, steelhead and trout populations through education, collaboration,
and advocacy. The annual conference provides a forum for restoration professionals to share progress and ideas from around the state.  We have regularly presented at this conference since 2004, and this year will host a field trip and present on Matilija Dam.

*  Ventura River Parkway Tour
    Thursday, March 20, 2014
 
* Dams: Learning to Live With and Without Them
   March 22 Saturday Morning Concurrent Sessions
   Matilija Dam: Taking Another Look - Paul Jenkin, Surfrider Foundation

See CalSalmon.org for the full agenda and to register for the conference.



DamNation - the film

The world premier of the new dam removal film will be at the South by Southwest Music and Film Festival, March 7 - 16, 2014 • Austin, TX.  We eagerly anticipate local screenings to reinvigorate the conversation on Matilija Dam.

"This powerful film odyssey across America explores the sea change in our national attitude from pride in big dams as engineering wonders to the growing awareness that our own future is bound to the life and health of our rivers. Dam removal has moved beyond the fictional Monkey Wrench Gang to go mainstream. Where obsolete dams come down, rivers bound back to life, giving salmon and other wild fish the right of return to primeval spawning grounds, after decades without access. DamNation’s majestic cinematography and unexpected discoveries move through rivers and landscapes altered by dams, but also through a metamorphosis in values, from conquest of the natural world to knowing ourselves as part of nature."

Watch the trailer here: http://www.damnationfilm.com



World Fish Migration Day, May 24th, 2014 -  World Fish Migration Day (WFMD) - we will be
working with NOAA and other partners to host an event to highlight the need for safe upstream and downstream passage for listed fish (i.e. steelhead).  Events will be taking place throughout the world, starting in New Zealand and working their way around the globe where they will finish here on the West Coast. More information can be found at:
http://www.wanningenwaterconsult.nl/en/products/world-fish-migration-day-2014


The Surfrider Foundation is the lead organization and fiscal sponsor for the Matilija Coalition, formed in 2000 to consolidate the NGO efforts to remove Matilija Dam from the Ventura River.

Tuesday, February 4, 2014

Surfers Point Winter 2014


A boardwalk is the most recent addition to the Surfers' Point Managed Shoreline Retreat project.  Designed to provide access around the 'cobble garden,' the boardwalk is constructed with weatherproof plastic decking and adds a finished touch to the bike path.  We have received positive comments from the 'regulars' at the beach, and people seem to be enjoying the little detour off the paved path.




The project also appears to be functioning well during winter "king tides" and storm surf.  This aerial overview shows the wet sand from high tide early in the day as well as the exposed cobble berm on the west (left) side of the project.




 The managed retreat project was designed to mimic and enhance the natural function of the beach which changes throughout the year.  The erosion of the beach in winter months is expected with high tides and surf, and wave action naturally sorts the sand and cobble.

This cobble, which was buried beneath sand just a month ago, extends beneath the dunes all the way back to the bike path.  The 'cobble berm,' which is is up to eight feet thick, provides a significant mass of natural river rock to protect the bike path from extreme events and future sea level rise.



















The aerial photos below were taken at extreme low (minus) tide, and clearly show the cobble in the intertidal zone - it is this cobble that provides the foundation for the marine delta that creates the "point" at the mouth of the Ventura River.





More about this project:  http://www.venturariver.org/search/label/Surfers%20Point


...